Skip to main content

Culvert Replacement at Greens Brook

Derby, Vermont

Nelson Farms, working with the Orleans County Natural Resources Conservation District, requests bids from qualified contractors to remove an existing 48-inch culvert and install a 33-foot long by 16-foot wide steel frame bridge with stone infill, headwalls, wingwalls, streambank restoration, and all associated work as outlined in the project bid plans in Derby, Vermont.

 

Project Schedule

Milestone Date
RFB Release Wednesday, March 18, 2026
Pre-Bid Meeting Wednesday, March 25, 2026, 10:00 am
Questions Due Friday, March 27, 2026, 5:00 pm
Answers Issued Tuesday, March 31, 2026, 5:00 pm
Bids Due Tuesday, April 7, 2026, 5:00 pm
Notice of Award Monday, April 13, 2026, 5:00 pm
Construction Begins After permit approval & pre-construction meeting June 16, 2026
Construction End  Thursday, October 1, 2026

 

 Project Documents

Downloadable RFB

Details of the project are provided in the Notice and Instructions to Bidders.

Electronic copies of the following will be emailed to contractors who request them or attend the pre-bid meeting and provide an email address:

➢ Project plans

➢ Advertisement for bid

➢ Bid documents

➢ Supporting specifications

 

To request documents or submit a bid, email:

Ted.Sedell@orleanscountynrcd.org